Building permit Toronto basics for 2026: you need a permit for structural or material alterations (adding or removing walls, new or enlarged windows and doors), additions, decks more than 60 cm (24 in.) above ground, sheds of 15 m² (161 sq ft) or more, new or modified plumbing and heating, a basement entrance or underpinning, and any second suite. Like-for-like work such as re-roofing without structural changes, replacing a window in the same opening of a house, new insulation, cabinets or a furnace replacement does not need one. In 2026 the City charges a $214.79 minimum, $11.53 per m² for interior alterations, and an extra 50% if work starts before the permit is issued.
Budgeting the work itself, not just the permit? Our deck cost calculator and basement renovation cost calculator give Ontario price ranges; the City permit fee in this guide is a separate line on top.
In this guide
At a glance: does your project need a building permit in Toronto?
| Project (house or small residential building) | Permit needed? | Condition (City of Toronto, July 2026) |
|---|---|---|
| Removing or adding interior walls | Yes | Any change to room sizes or uses |
| New window or door, or enlarging one | Yes | New opening, or a bigger or moved opening |
| Replacing a window or door in the same opening | No | Detached, semi or single-unit row house; same size and location, structure not affected |
| Deck | Yes, if over 60 cm | No permit if uncovered, 60 cm (24 in.) or less above grade, not a required exit, zoning respected |
| Shed | Yes, if 15 m² or more | No permit under 15 m², one storey, detached, storage only, no plumbing |
| Detached garage, workshop, pool house | Yes, if over 10 m² | Any size if attached or if it has plumbing |
| Finishing a basement | Depends | Permit if structural work, new plumbing or heating, underpinning, basement entrance or second suite |
| Second suite (basement apartment) | Yes | Always |
| Re-roofing | No | Only if no structural work |
| Insulation, cabinets, furnace or boiler replacement | No | Listed as exempt by the City |
| Repairing or replacing plumbing fixtures | No | Like-for-like only; new plumbing needs a permit |
| Backwater valve | Yes | Sump pump alone: no permit |
| Wood stove, fireplace or chimney | Yes | Install or reconstruct |
Two rules sit above this table. First, the list on the City page is “not exhaustive”. Second, even when no building permit is needed, the City says the work must still comply with the Zoning By-law (setbacks, height, lot coverage). When in doubt, check before you build.
When you need a building permit in Toronto
The legal basis is Ontario’s Building Code Act, 1992: section 8(1) says no person shall construct or demolish a building unless a permit has been issued by the chief building official. The City of Toronto page “When do I need a building permit?” (modified July 21, 2026) turns that into a practical list. You need a permit to:
- Build a new building or an addition, such as a second or third storey, an attached garage, carport, sunroom, porch or deck.
- Make structural or material alterations: add or remove walls, cut new windows or doors, enlarge or relocate existing ones, or enclose an existing deck, porch or patio of any size.
- Replace windows or doors in buildings other than a detached, semi-detached or row house with a single dwelling unit (a duplex or a triplex, for example).
- Build a deck more than 60 cm (24 in.) above ground.
- Build a shed of 15 m² (161 sq ft) or more, or another accessory structure larger than 10 m² (107 sq ft) such as a detached garage, workshop or pool house.
- Finish a basement when the work includes structural changes, new or modified heating or plumbing, excavation or foundations, underpinning, a basement entrance or a second suite.
- Install or modify heating or plumbing systems, a backwater valve or a backflow prevention device.
- Install or rebuild a chimney or fireplace, or install a wood-burning stove.
- Build a retaining wall over 1 m (3 ft 3 in.) next to public property, a building entrance or a private area open to the public.
- Demolish all or part of a building, or change a building’s use, even with no construction.
Rooftop solar collectors and solar hot water systems, green roofs and wind turbine supports over 3 kW are also on the City’s permit list.
Renovations that do not need a permit
The same City page lists work that is exempt in a house. The most useful items for homeowners:
- Adding or replacing insulation.
- Replacing roofing material when no structural work is needed.
- Replacing a window or door in an existing opening of a detached, semi-detached or single-unit row house, if the size and location stay the same, the structural support is not affected and no new exit is created.
- Replacing a furnace or boiler in a house; adding a cooling system, gas fireplace, air cleaner, in-line humidifier or hot water tank.
- Repairing and replacing plumbing fixtures.
- Installing cabinetry and millwork.
- Basement waterproofing repairs and installing a sump pump.
- Finishing a basement with no structural or material change, no new unit and no new plumbing.
- A skylight in a house of 3 storeys or less, if no more than one rafter or joist is removed (trusses excluded).
- Re-cladding a house of 3 storeys or less with non-combustible material other than brick or stone veneer.
- Seasonal plastic-covered canopies (driveway tents) installed on or after October 15 and removed by April 15.
RénoClair tip
Exempt from a building permit does not mean exempt from every rule. The City still expects zoning compliance, almost all electrical work needs a separate permit from the Electrical Safety Authority (ESA), and a contractor’s “you don’t need a permit” does not protect you: the City says the homeowner pays any fee or penalty, even if a contractor assured you that permits were not needed.
Decks, sheds and garages: the size limits
For outdoor projects, the deciding numbers are height and area. A deck whose finished level is more than 60 cm (24 in.) above the adjacent finished grade needs a permit; so does any deck attached as an addition and any deck, porch or patio you enclose, whatever its size. The City’s decks and porches guide (modified August 27, 2026) asks for a site plan or survey with setbacks, a zoning summary, and drawings showing footing size, spacing, depth and frost protection, beam and column spans, stairs and guards. Deck and porch permits are now applied for online through the City’s Express permit portal, and the 2026 fee is a flat $214.79.

A shed is exempt only if it meets all five conditions: under 15 m² (161 sq ft) in gross area, one storey, not attached to any building or structure, used only for storage, and without plumbing. A detached garage, workshop, carport, pool house or cabana needs a permit once it is larger than 10 m² (107 sq ft), and at any size if it is attached or has plumbing. Planning a deck? Our deck cost calculator estimates the build itself by province.
Basements and secondary suites
Finishing a basement is the project homeowners most often get wrong. Drywall, flooring and paint over an existing open basement, with no new plumbing, no structural change and no new unit, does not need a permit in Toronto. Add a bathroom (new plumbing), move a load-bearing wall, extend heating ducts, underpin, lower the floor or cut a separate entrance, and it does. The City’s interior alterations guide (modified October 16, 2026) asks for floor plans showing all plumbing fixtures and the location of smoke and carbon monoxide alarms, sections and construction details; for one- and two-unit houses, no plumbing drawings are required unless the project includes a reverse-sloping driveway, but a Plumbing Data Sheet is.

A basement apartment is a second dwelling unit and always needs a permit. The City’s secondary suites guide (modified November 3, 2026) asks for a site plan with a zoning summary and parking, floor plans with smoke and CO alarms, sections and construction details, plus a Rental Renovation Licence Screening Form. The 2026 fee is the interior alteration rate plus a $56.33 residential unit fee. If water is the reason for your basement work, note that a backwater valve needs its own permit, while a sump pump alone does not; our guide to basement waterproofing cost in Ontario covers prices and the Toronto subsidy.
Windows, roofing, furnaces and electrical work
Most like-for-like replacements are exempt. Replacing windows in the same openings of a detached, semi or single-unit row house needs no permit (prices are in our guide to window replacement cost in Ontario); enlarging an opening, or replacing windows in a duplex or larger building, does. Re-roofing is exempt unless structural work is needed. Replacing a furnace or boiler in a house is on the City’s no-permit list, but new ductwork or a new heating system is not; see our furnace replacement cost guide for Ontario for the full installed price.
Electrical work is a separate track. The City’s BuildSafeTO page reminds owners that almost all electrical work needs an electrical permit from the Electrical Safety Authority (ESA), obtained separately from the City building permit. That applies to a service upgrade, a sub-panel or an EV charger circuit; our 200 amp panel upgrade cost guide explains that process.
Building permit Toronto fees in 2026
Toronto calculates most fees with one formula: permit fee = service index × floor area of the work (m²), with a minimum of $214.79 for all work. Some items are flat fees. The rates below come from the City’s building permit fees page (fees effective January 1, 2026; page modified June 19, 2026).
| Type of work (residential) | 2026 City fee | How it is charged |
|---|---|---|
| Minimum fee, all work | $214.79 | Applies when the formula gives less |
| Interior alterations (houses, Group C) | $11.53 | Per m² of floor area of the work |
| Basement finishing in a dwelling or townhouse | $6.20 | Per m² |
| New house or addition (single family, semi, townhouse, duplex) | $18.56 | Per m² |
| Each new residential unit (e.g. a second suite) | $56.33 | Per unit, on top of the area fee |
| Deck, porch or carport | $214.79 | Flat fee |
| Detached garage or accessory structure | $214.79 | Flat fee, each |
| Fireplace or wood stove | $214.79 | Flat fee, each |
| Plumbing fixture (single family dwelling) | $23.20 | Each fixture |
| Buried piping, single family (water service, sanitary, storm) | $214.79 | Flat fee |
| Backwater valve or sump complete with pump | $38.67 | Each |
| HVAC alteration: add-on system or ductwork (house) | $214.79 | Flat fee |
| Construction started before the permit | 50% of the permit fee | Minimum $214.79, maximum $29,456.99 per permit |
Other City charges you may meet: $92.79 per hour for extra examination or inspection work, the greater of $214.79 or $92.79 per hour for revised information after you apply, and $214.79 to transfer a permit. These are the rates in effect since January 1, 2026; check the fee page for the year you apply.
Worked example: permit fees for a basement with a new bathroom
A Toronto semi-detached house. The owners finish 65 m² (about 700 sq ft) of basement, add a three-piece bathroom (toilet, sink, shower) and extend two heating ducts. New plumbing and heating changes mean a permit is required. Using the 2026 City rates:
| Item | Calculation | City fee |
|---|---|---|
| Basement finishing | 65 m² × $6.20 | $403.00 |
| Plumbing fixtures | 3 × $23.20 | $69.60 |
| HVAC ductwork alteration | Flat fee | $214.79 |
| Total with a permit issued before work starts | $687.39 | |
| Work-without-permit fee if they had started first | 50% of $687.39 (above the $214.79 minimum) | $343.70 |
| Total if caught after starting | $1,031.09 |
Starting before the permit would cost these owners $343.70 more in City fees alone, before any stop-work delay or the cost of opening finished walls for inspection. Two quick comparisons using the same rates: removing walls across 40 m² of a main floor is 40 × $11.53 = $461.20; a small 10 m² alteration works out to $115.30 on the formula, so the $214.79 minimum applies. This is an estimate from the published rates; the City calculates the official fee when it reviews your application, and the ESA electrical permit is extra. To price the renovation itself, run your own dimensions in our basement renovation cost calculator.
Working without a permit: what it can cost
The City’s “Working without a permit” page lists what happens if you find out you need a permit after work has started:
- A “work without permit” administrative fee equal to 50% of the permit fees (in 2026: at least $214.79, at most $29,456.99 per permit).
- A delay while the application is processed. All work must stop during this time, and the normal timeline and fees still apply.
- Possibly having to undo the work, or doing more work than planned, such as extra structural or mechanical work.
- Possible legal or financial problems later, for example when selling the house or making an insurance claim.
The City is explicit that the homeowner pays these fees or penalties, even if a contractor said no permit was needed. Section 8(1) of the Building Code Act prohibits construction without a permit, and the City warns that failing to obtain permits can lead to costly delays, legal action or removal of completed work.
How to get a building permit in Toronto: step by step
- Check whether you need one. Use the City list above; the City also offers a voluntary pre-check tool to spot problems before you apply.
- Check zoning. Setbacks, height and lot coverage apply even to exempt work. Additions need a zoning summary on the site plan.
- Prepare drawings. You may draw them yourself if you have the drafting skills and know the Ontario Building Code; otherwise a qualified designer with a Building Code Identification Number (BCIN), an architect or an engineer prepares them. Drawings must show the designer’s name, registration number, BCIN and signature.
- Fill in the forms. Typically the Application to Construct or Demolish, Schedule 1 (designer information), and depending on the project a Plumbing Data Sheet, Tree Declaration, Energy Efficiency Design Summary (additions) and Rental Renovation Licence Screening Form.
- Submit online. Decks and porches go through the Express portal; most other residential projects through the Toronto Building online application submission. According to BuildSafeTO, staff check within one business day whether the submission is complete; missing documents are the most common cause of delay.
- Pay the fees and wait for plan review. A plan examiner reviews zoning and Building Code compliance and may ask for corrections.
- Build and book inspections. Inspections are requested online, and a final inspection is required to close the permit.

Do not let an issued permit sit. Under section 8(10) of the Building Code Act, the chief building official may revoke a permit if the work has not been seriously commenced six months after it was issued, or if it is substantially suspended for more than one year. Additions over 100 m² also require a Residential Infill Construction Public Notice posted on site (small residential additions guide).
Before you sign a renovation contract: permit checklist
- The contract says who applies for the building permit and who pays the fee, and work does not start until the permit is issued.
- For electrical work, the contract names who takes out the ESA permit.
- The drawings come from you (if qualified) or from a designer with a BCIN, an architect or an engineer.
- The quote lists the permit fee as its own line, using the current City rates.
- Inspections are built into the schedule, including the final inspection that closes the permit.
- If a contractor says no permit is needed for work on the City list (walls, new plumbing, a deck over 60 cm), ask them to show you the exemption in writing.
- Keep the permit, inspection records and drawings with your house documents; open permits can complicate a sale.
Common mistakes Toronto homeowners make
- Assuming a basement never needs a permit. A bathroom, moved walls, ductwork or a side entrance change the answer.
- Measuring the deck from the wrong place. The 60 cm limit is the finished deck level above the adjacent finished grade, and enclosing a deck needs a permit at any height.
- Building a 16 m² shed. The exemption stops below 15 m² (161 sq ft), and a shed with plumbing always needs a permit.
- Treating the building permit as the only one. Electrical work needs an ESA permit, and zoning still applies to exempt work.
- Starting “just the demolition” early. Demolishing part of a building is itself on the permit list, and the 50% work-without-permit fee applies once construction begins.
Frequently asked questions
Do I need a building permit in Toronto to renovate a kitchen or bathroom?
Not if you only replace cabinets, counters and existing plumbing fixtures in place. You need a permit if you remove or add walls, add new plumbing (a new fixture location), change heating, or create new window or door openings.
How much is a building permit in Toronto in 2026?
There is a $214.79 minimum. Interior alterations cost $11.53 per m², basement finishing $6.20 per m², additions $18.56 per m², and decks a flat $214.79. A 65 m² basement with a new bathroom and duct changes comes to about $687.39 in City fees. For the renovation itself, try our basement renovation cost calculator.
Deck building permit Toronto: when is one required?
Yes if the finished deck level is more than 60 cm (24 in.) above the ground, if it is enclosed, or if it is part of a required exit. A low, uncovered deck that respects the Zoning By-law needs no permit. The 2026 fee is $214.79.
Do I need a permit to finish my basement in Toronto?
Only if the work includes structural changes, new or modified plumbing or heating, underpinning, excavation, a basement entrance or a second unit. Drywall, flooring and paint in an open basement with none of these do not need one.
Do I need a permit for a shed in Toronto?
Not if it is under 15 m² (161 sq ft), one storey, detached, used only for storage and has no plumbing. A shed of 15 m² or more needs a permit.
Do I need a permit to replace windows or a roof in Toronto?
No for same-size windows in the existing openings of a detached, semi or single-unit row house, and no for re-roofing without structural work. Yes for new or enlarged openings and for window replacement in duplexes and larger buildings.
What happens if I renovate without a permit in Toronto?
The City adds a fee of 50% of the permit fees (minimum $214.79, maximum $29,456.99), work must stop until the permit is processed, and you may have to open or undo work. The homeowner pays, even if the contractor said no permit was needed.
How long does a building permit take in Toronto?
The City checks within one business day whether your submission is complete, then a plan examiner reviews it; the City gives no fixed number of days on its guide pages. Complete drawings and forms are the best way to avoid delays.
The bottom line
In Toronto, the permit question turns on a handful of thresholds: structure and openings, new plumbing or heating, decks over 60 cm, sheds of 15 m² or more, accessory buildings over 10 m² and any new unit. Like-for-like replacements (roofing, same-opening windows in a house, insulation, cabinets, a furnace) are exempt. In 2026 the fee starts at $214.79 and is mostly area-based, which makes it small next to the 50% penalty, the stop-work delay and the risk of tearing out finished work. Apply first, book inspections, close the permit, and budget the renovation itself separately, for example with our deck or basement cost calculators.
If your permitted project is an energy upgrade, the City also offers a loan for it: see our guide to the Toronto Home Energy Loan Program for the 2026 rates and rules.
Sources
- City of Toronto, When do I need a building permit? (modified July 21, 2026), read November 25, 2026.
- City of Toronto, Building permit fees (fees effective January 1, 2026; page modified June 19, 2026), read November 25, 2026.
- City of Toronto, Working without a permit (modified October 24, 2025), read November 25, 2026.
- City of Toronto, Decks and porches (modified August 27, 2026), Interior alterations (October 16, 2026), Secondary suites (November 3, 2026) and Small residential additions (October 2, 2026), read November 25, 2026.
- City of Toronto, BuildSafeTO: learn about building permits (modified September 17, 2026), read November 25, 2026.
- Government of Ontario, Building Code Act, 1992, S.O. 1992, c. 23, sections 8(1) and 8(10), e-Laws consolidation read November 25, 2026.
- Fee amounts in the worked example are RénoClair calculations from the City’s published 2026 rates, not an official City estimate.