How much should you set aside for surprises, and how much should you hold back from the final payment? This calculator sizes your contingency reserve by type of work and home age, tracks up to 4 change orders and calculates your province’s completion holdback. Example: a $35,000 bathroom contract in a 1975 home = a reserve of about 15%, or $5,250 before tax.
Calculate Your Contingency Reserve, Track Change Orders & Protect Your Payments
Enter your signed or estimated contract price, select your project risk profile and home age, and track change orders (avenants) in real time against your contingency reserve.
5. Change orders ($ before tax)
How the reserve is calculated
| Factor | Effect on the reserve |
|---|---|
| Surface work (painting, flooring, fencing) | 8% |
| Envelope and equipment (roof, windows, heat pump) | 10% |
| Kitchen, bathroom, basement, plumbing or electrical | 13% |
| Foundation or structure | 18% |
| Home built before 1960 | +5 points |
| Home built 1960–1989 | +2 points |
| Home built 2010 or later | −1 point |
| Risks you tick (opened walls, slab cutting, possible asbestos or vermiculite, custom materials) | A few points each |
These percentages are prudent benchmarks, not an official rule. The most common surprises once walls are opened: aluminum or old ungrounded wiring, an undersized panel (see the electrical panel upgrade cost calculator), cast-iron drains, rot under a shower, and materials in older homes that may contain asbestos and must be tested before work starts.
Change orders: keep control of the budget
- Ask for a written, signed change order with a price before extra work begins.
- Pay change orders out of the reserve, not by raising scheduled payments.
- The calculator warns you when change orders reach 75% and then 100% of the reserve.
Completion holdback by province
| Province | Holdback | Period | Law |
|---|---|---|---|
| Quebec | No mandatory statutory holdback; 10% is a prudent contract practice | Until 30 days after the end of work, plus signed releases | Civil Code arts. 2726 and 2727 (legal hypothec) |
| Ontario | 10% mandatory | 60 days after completion or the certificate of substantial performance | Construction Act |
| British Columbia | 10% mandatory | 55 days after completion | Builders Lien Act |
| Alberta | 10% mandatory | 60 days (90 days for some concrete work) | Prompt Payment and Construction Lien Act |
Check the contractor before signing
- Quebec: an active Régie du bâtiment (RBQ) licence that covers the work; a written contract for residential work.
- Ontario: an electrical contractor licensed by the Electrical Safety Authority (ESA); some cities, such as Toronto, also require a municipal renovator licence.
- British Columbia: electrical and gas work by companies authorized by Technical Safety BC.
- Alberta: a Prepaid Contracting licence if the contractor asks for a deposit before finishing the work.
To track price increases in your city, see renovation costs by city. Taxes are shown separately: 14.975% GST + QST in Quebec, 13% HST in Ontario, and 5% GST in British Columbia and Alberta. In BC, the contractor pays the 7% PST on materials and includes it in the price for work that becomes part of the house. To add up several projects, use the multi-room renovation budget planner.
Frequently asked questions
What contingency percentage should I use for a renovation?
From 8% for surface work in a newer home to more than 20% for foundation work in a pre-1960 home. For a kitchen or bathroom in a 1960–1989 home, about 15%.
Is there a statutory holdback in Quebec?
No. Quebec does not require one, but subcontractors and suppliers who declared their contract to the owner can publish a legal hypothec up to 30 days after the end of work. Keeping about 10% until then and getting signed releases is a common precaution.
What is the holdback in Ontario?
10% of the price, kept for 60 days after completion or publication of the certificate of substantial performance, under the Construction Act.
What is a change order?
A written amendment to the contract that changes the work, the price or the schedule. Sign it before the extra work starts.
What if the reserve runs out?
Stop non-essential additions, ask for a fixed price on every new change order, and move optional finishes to a later phase.